This project was conducted by Impact Services Incorporated for the LeSueur County Highway Department. They planned to use the site area as a source of fill in the construction of Bridge 4090 and adjacent road grades. This Phase III data recovery project included patterned surface reconnaissance, excavation and scraping procedures. A total of 49 artifacts were recovered from the site which appeared to have been a short-term Woodland habitation which was utilized infrequently.
| A Phase III Archaeological Data Recovery of a Site Along CSAH 3, Bridge 5090, LeSueur County, Minnesota. Richard Strachan and Kathleen Roetzel. 1993. |