The Implementation Plan identifies specific project budgets and schedules based on project scope and priorities developed during the Concept. The Implementation Plan divides individual projects into related "Groups" and then schedules them in a sequential manner based on priorities, funding and dependency on previous projects.
Project Budget Basis Project costs consist of "hard" (probable construction cost) plus Technology Infrastructure (Tech) at 6 percent of hard costs, Furniture, Fixtures and Equipment (FF&E) at 7 percent; plus "soft" costs (approvals, surveys, testing & design) at 15 percent. This is illustrated in Table 8.1. Project Budgets are estimated based on mid-year 2001 construction costs. Table 8.2 delineates the rate increase multiplier for a particular year using the base 2001 cost estimate. The per square foot cost ranges used in the Implementation Plan for various levels of work are noted in the following table.
Table 8.1 Project Cost Square Per Square Foot Basis
| Level of Work | 'Hard Cost' $/GSF | Tech $/GSF |
FF&E $/GSF |
'Soft Cost' $/GSF |
Project Budget $/GSF |
| New Construction (highly technical) | $ 250 | $ 15 | $ 18 | $ 37 | $ 320 |
| New Construction (non-technical) | $155 | $9 | $11 | $23 | $198 |
| Major Renovation (highly-technical) | $200 | $12 | $14 | $30 | $256 |
| Major Renovation (non-technical) | $125 | $8 | $9 | $19 | $160 |
| Minor Renovation | $45 | $3 | $3 | $7 | $58 |
| Relocation Only | $7 | $2 | $0 | $1 | $10 |
Site project budgets were generated in a similar manner based on square foot or lump sum amounts.
Table 8.2 Cumulative Inflationary Multipliers of 2001 $ Based on an Assumed 4% Yearly Escalation Rate.
| YEAR | MULTIPLIER | YEAR | MULTIPLIER |
|---|---|---|---|
| 2002 | 100.00% | 2008 | 131.59% |
| 2003 | 104.00% | 2009 | 136.86% |
| 2004 | 108.16% | 2010 | 142.33% |
| 2005 | 112.49% | 2011 | 148.02% |
| 2006 | 116.99% | 2012 | 153.95% |
| 2007 | 121.67% | 2013 | 160.10% |
| 2008 | 126.53% | 2014 | 166.51% |